POs, HES and approvals

Many corporate customers will not pay an invoice that does not cite their purchase order (OC, orden de compra). In that world, issuing first and asking for the PO afterwards is the fastest way to end up with an unpaid invoice and a credit note ahead of you.

Relvo reverses the order: the commercial reference is requested from the charge calculation, before issuance, and until it arrives the charge calculation is visibly blocked.

A commercial reference can be the buyer’s document that authorizes the spend, or a prior tax document that the new document must cite.

Reference Typical use SII code
Purchase order (OC) Customer’s purchase authorization 801
Order note (nota de pedido) Formal order prior to the PO 802
HES Service acceptance sheet alphanumeric
Invoice Document being corrected or continued 33 · 34 (exempt)
Credit note Prior correction being cited 61
Debit note Prior correction being cited 56
Dispatch guide (guía de despacho) Associated delivery 52
Export invoice Export transaction 110

Beyond type, number and date, a reference captures the issuer’s tax identity, the country, the net and total amounts, and—where applicable—the declared exchange rate. That makes it possible to compare what the PO authorizes with what the charge calculation computes, before issuance.

If the reference arrives as an attached document, Relvo extracts those fields and flags the result as pending review when the extraction was inconclusive.

The status of the reference and the status of its attached document are different things: a reference can be registered with manually entered data and no file at all.

Reference status

Status Meaning
Registered The data was captured
Verified An operator confirmed the data. Unblocks issuance
Superseded A later version exists, for example a corrected PO
Rejected Reviewed and found invalid
Voided Withdrawn from operational use, kept for audit

Attachment extraction status

Pending → processing → accepted · needs review · failed.

A superseded or voided reference is never deleted: it is kept so that, months later, you can explain why an invoice was issued citing that PO and not another.

Example

Acme, July close

  1. The July charge calculation comes to USD 1,639.40 and the contract requires a PO.
  2. Relvo sends the request from the charge calculation; the charge calculation shows as blocked for issuance.
  3. Acme replies with PO no. 4500192387 for USD 20,000 per year.
  4. An operator verifies it. The block is lifted.
  5. The invoice is issued citing the PO as a commercial reference, code 801.

In August the same PO is still valid: the block does not have to be cleared from scratch every month.

If the PO authorizes less than the charge calculation computes, the answer is not to issue anyway. It is to correct the charge calculation, or obtain an expanded PO, and record which of the two happened. Issuing above the PO produces an invoice the customer will reject under its own internal controls.